New Path Request process TTP 2025 – Roadmap towards Path Request submission deadline

  • Data dumps:​
    • 21.11.2023:​
      • PCS Test 2 and 3: all existing data will be replaced with production data​
      • PCS Test 4 and 5: all existing data will be deleted and only the Reference Data from production will be imported​
    • Shortly after 23.01.2023 (PaPs publication): PaPs information to all sites 
    • Between 05.02.2023 and 09.02.2023: IMs will receive an overview of their reference data (except operations points) registered in PCS. 
    • Middle/end of March 2023: PCS Test 2 and Test 3 – All existing data will be replaced with production data
    ​ 
  • 08.04.2024: submission deadline​ 
  • RNE to send a list of Path Request messages with incorrect Train Information (issue: one PR linked to more than Train variant)