Code | TypeOfInformation | Phase | Actor | Target phase | Action |
30 | create dossier | Harmonization | LA | Harmonization Conference | Start Feasibility Study |
31 | close dossier | Harmonization Conference | LA/LIM | Harmonization | Back to Harmonization |
05 | path study request | Harmonization Conference | LA | Feasibility Study Request | Submit FS request |
07 | create offer | Feasibility Study Request | LIM/PCS | Feasibility Study Elaboration | Release FS Elaboration |
02 | harmonization – accepted | Harmonization Conference | IM | Set the acceptance indicator to green as IM | |
03 | harmonization – rejected | Harmonization Conference | IM | Set the acceptance indicator to red as IM | |
01 | harmonization – in process | Harmonization Conference | IM | Set the acceptance indicator to yellow as IM | |
02 | harmonization – accepted | Harmonization Conference | RA | Set the acceptance indicator to green as RA | |
03 | harmonization – rejected | Harmonization Conference | RA | Set the acceptance indicator to red as RA | |
01 | harmonization – in progress | Harmonization Conference | RA | Set the acceptance indicator to yellow as RA | |
29 | withdrawal | Feasibility Study Elaboration | LA | Harmonization | Withdraw FS |
42 | preparation of draft offer – accepted | Feasibility Study Elaboration | IM | Set the acceptance indicator to green as IM | |
43 | preparation of draft offer – rejected | Feasibility Study Elaboration | IM | Set the acceptance indicator to red as IM | |
08 | coordination update | Feasibility Study Elaboration | IM | Set the acceptance indicator to yellow as IM | |
09 | draft offer | Feasibility Study Elaboration | LIM | Feasibility Elaboration Conference | Release FS Conference |
07 | create offer | Feasibility Elaboration Conference | LIM | Feasibility Elaboration Conference | Return to FS Elaboration |
02 | harmonization – accepted | Feasibility Elaboration Conference | RA | Set the acceptance indicator to green as RA | |
03 | harmonization – rejected | Feasibility Elaboration Conference | RA | Set the acceptance indicator to red as RA | |
11 | observation in process | Feasibility Elaboration Conference | RA | Set the acceptance indicator to yellow as RA | |
14 | preparation of final offer – accepted | Feasibility Elaboration Conference | IM | Set the acceptance indicator to green as IM | |
15 | preparation of final offer – rejected | Feasibility Elaboration Conference | IM | Set the acceptance indicator to red as IM | |
13 | preparation of final offer – in process | Feasibility Elaboration Conference | IM | Set the acceptance indicator to yellow as IM | |
16 | final offer | Feasibility Study Elaboration | LIM | Feasibility Study Result | Submit FS result |
07 | create offer | Feasibility Study Result | LIM | Feasibility Study Elaboration | Withdraw FS result |
17 | final offer accepted | Feasibility Study Result | LA | Harmonization | Acknowledge FS Result |
02 | harmonization – accepted | Feasibility Study Result | RA | Set the acceptance indicator to green as RA | |
03 | harmonization – rejected | Feasibility Study Result | RA | Set the acceptance indicator to red as RA |